Demolition and repaving scheduled for south side of Market St this week

Work to replace the aging water main at 24th Ave NW and NW Market St is complete, as crews also wrap up paving work on the center lane of Market.

According to SDOT, work has now shifted to the south side of Market St as crews begin demolition and concrete cutting work. The traffic flow is now on the north side of Market St, with one lane in each direction east/west between 24th Ave and 54th Ave.

Old pipe, new pipe. (Courtesy SDOT)

SDOT says the work on the south side should take a week and half, with conduit work beginning late this week.

Crews will also pave the southwest curb extension at 24th Ave NW and Market intersection late this week or next week.

More work will simultaneously continue on NW 54th St, including excavating pole foundations and pouring foundation bases, along with road excavation and grading.

SDOT says the upcoming work will impact pedestrians, as they’ll be working on various sections of the sidewalks along Market. There will be detours in place along the project corridor.

For more about the project, visit the Ballard Multimodal Corridor website.